Schedule Revision: Notice of Annual High-Voltage Substation Maintenance and Power Outage (Main Campus, 2026)
https://construc.site.nthu.edu.tw/p/406-1167-303535,r7725.php?Lang=en
Locations Affected: Please refer to the attached schedule.
Duration: Please refer to the attached schedule.
Schedule Revision for Campus Power Outages:
【Important Schedule Update】 To accommodate specialized research experiments and instructional needs in certain buildings, the maintenance schedule for the MOF2 Circuit High-Voltage Substation has been revised as follows:
- July 12, 2026 (Sunday) – Revised Outage Locations:
College of Humanities and Social Sciences (CHSS)、Life Science Building II、Life Science Building I、Biotechnology Building. (Note: The following facilities, originally scheduled for an outage on this date, will NOT lose power: Nuclear Reactor Division, Isotope Division, Ion Accelerator Laboratory, Photo-Electronics Laboratory, Department of Biomedical Engineering and Environmental Sciences, and the South Campus Wastewater Treatment Plant.)
- August 2, 2026 (Sunday) – Revised Outage and Maintenance Areas:
- Rescheduled Facilities from July 12 (Added to today's annual maintenance): Nuclear Reactor Division, Isotope Division, Ion Accelerator Laboratory, Photo-Electronics Laboratory, Department of Biomedical Engineering and Environmental Sciences (Engineering Building II), and the South Campus Wastewater Treatment Plant. (The annual facility and equipment maintenance for these locations has been moved from July 12 to today.)
- Original August 2 MOF2 Circuit Schedule: Power outages for all other regularly scheduled buildings on this day will remain unchanged.
Reason for Outage:
- Scheduled annual maintenance and safety inspection of all high-voltage substation facilities and equipment across the campus.
- During the outage, all departments, institutes, and dormitory units within the affected areas must unplug all computers and laboratory equipment, and power supplies at distribution boards and switch boxes should be disconnected for safety and to prevent damage during power restoration.
- Physical notices will be posted in addition to this email. If work finishes early, power will be restored without notice. We apologize for the inconvenience.
- The end times in the schedule are estimates based on inspection progress.
- Early Completion: Power will be restored early without further notice.
- Unforeseen Delays: Restoration may be delayed if emergency repairs are needed.
- If you have scheduled important meetings or activities during this time, please assess the impact and consider a backup plan or rescheduling due to potential changes in work progress or restoration times.
Your cooperation in preparing for this outage in advance is greatly appreciated.
General Affairs Section (Maintenance and Construction Group)
Point of Contact: Mr. Hsu
Extension: 35253
Email: myhsu@mx.nthu.edu.tw
Date: June 25, 2026(Update)
|